01 Definitions
Terminology
Requirements Specification
-
created by the customer as basis of discussion
-
defines what must be delivered
-
Functions
-
Quantities
-
Quality (clear and understandable)
-
Constraints
basis for discussion and potential implementationreference document-
contractual binding if accepted and signed by both sides
-
crucial if the supplier fulfilled the agreement
-
whether the payment is due, in case of disputes or acceptance testing
Only this document is reference is no others are explizit listedCategory English Term Purpose / Content Contractual Status Examples Contractual Baseline Requirements Specification / Statement of Work (SoW) Defines *what* must be delivered and accepted. Binding when referenced or signed. Customer Requirements Spec, Lastenheft, SoW, Contract Appendices Technical Documents Technical Specification / System Design Specification Describes *how* requirements will be met. Binding only if approved or referenced. Design Spec, Pflichtenheft, Implementation Plan Clarification Documents Supplier’s Comments on Requirements / Clarification Report Capture supplier feedback or open points before approval. Informative, may become binding after agreement. Lastenheft-Stellungnahme, Review Notes Supporting Documents Presentations / Meeting Notes / PDFs / Emails Support communication and understanding. Not binding unless formally included. PowerPoints, Workshop Notes, Emails Change Records Change Request (CR) / Engineering Change Notice (ECN) Document approved changes to the agreed scope. Binding once approved and integrated. Change Log, Updated Requirements Requirements
“Something the customer wants from us”
-
A condition that must be satisfied for the output of a work effort to be acceptable
-
explicit, objective, clear and often quantitative description
Tasks
“Something we are planning to give to the customer”
-
Packages of work that describe how requirements are implemented
Milestones
-
Work results that shall be delivered at a certain point in time
Relationships
-
One task refers to one or more requirements
-
One milestone groups one or more tasks
Remaining Effort (days)
We distinguish three complementary views on the remaining effort:
-
Remaining budget (d) = planned (d) – actual (d) → How many days of the original budget are still available. Can become negative if the budget is exceeded.
-
Remaining effort (plan) (d) = planned (d) × (1 – progress) → How many days should be left according to the original plan and reported progress.
-
Remaining effort (forecast) (d) = (actual (d) / progress) – actual (d) → Estimated remaining effort based on current efficiency (extrapolation of actual performance).
These values provide insight into budget consumption (remaining budget), plan status (plan), and expected outcome (forecast).